AIM - Application Implementation Methodology
Function Activities Documents
1 Definition CR010
2 Operational Analysis As Is RD10, RD20, RD50
3 Solution Design To Be BR30, BR10
4 Build Set up BR100
5 Transition Testing TE40, MD50, MD70
6 Production User manual GO LIVE
Document No Description
1 CR010 Project Management Plan
2 RD10 Identify Current Financial and Operating Structure
3 RD20 Conduct Current Business Baseline
4 RD 50 Gather Business Requirement
5 BR030 Business Requirement Solution
6 BR010 Gap Analysis
7 MD050
8 MD070 Technical Solution for Functional Design
9 BR100 Define Application Set ups (Set Up / Build)
10 TE020 Test - Unit level
11 TE040 Test Scripts
12 TE 050 Integration (CRP)
Sl.No.
Project Mgmt Plan (PMP)
Sl.No.
Gaps are to be customised and will be build Solution from Functional Design